Working Principle of Cement Silo

2022/03/30 16:34

1. Whilst the cement silo works, it need to be erected by means of a unique crane, and then located on the pre prefabricated concrete foundation. test the verticality of the cement silo with the horizontal plane after erection, and then weld its backside firmly with the foundation embedded components.


2. After the garage bin is fixed, the cement is transported to the construction website online with the aid of the cement truck, and then the conveying pipeline of the cement truck is connected with the feeding pipeline of the cement bin, and the cement inside the bin is transported to the cement bin thru the gas pressure of the cement truck.


3. In the system of conveying cement to the storage bin, the operator constantly presses the button of the vibration motor of the dust collector to shake off the cement connected to the material bag of the dirt collector to prevent blockading the cloth bag and bin explosion.


4. Once the cloth bag is blocked and the strain inside the warehouse exceeds the safety stress of the stress safety valve at the top of the warehouse, the pressure protection valve may be opened to release the stress within the warehouse to save you the occurrence of warehouse explosion accident.


5. Via the excessive and low cloth levels, it can be determined that the warehouse is full and quick of cloth.